3 activating/deactivating sunny portal, 4 testing the connection to sunny portal, Activating/deactivating sunny portal – SMA WEBBOX-BT-20 User Manual
Page 58: Testing the connection to sunny portal
Managing Plant Data
SMA Solar Technology AG
58
SWebBox20-BA-en-13
User Manual
8.2.3 Activating/Deactivating Sunny Portal
Activating data transmission to Sunny Portal
Requirement:
You must be registered in Sunny Portal (see Section 8.2.2 ”Registering Sunny WebBox in Sunny
Portal” (page 57)).
1. Select the Sunny WebBox in the plant tree and select "Settings" in the device menu.
2. Select the "Sunny Portal > Basic settings" parameter group.
3. Select [Edit].
4. In the "Use Sunny Portal" field, select "Yes" in order to use Sunny Portal. Depending on the
configured upload frequency, the Sunny WebBox automatically transmits the PV plant data to
Sunny Portal.
5. Select [Save].
Deactivating data transmission to Sunny Portal
1. Select the Sunny WebBox in the plant tree and select "Settings" in the device menu.
2. Select the "Sunny Portal > Basic settings" parameter group.
3. Select [Edit].
4. In the "Use Sunny Portal" field, select "No" in order not to use Sunny Portal (default setting).
5. Select [Save].
8.2.4 Testing the Connection to Sunny Portal
You can test the connection to Sunny Portal. You do not need to register in Sunny Portal to do this.
1. Select the Sunny WebBox in the plant tree and select "Settings" in the device menu.
2. Select the "Sunny Portal > Status and Actions" parameter group.
3. In the "Portal connection test" field, select "Execute".
☑ The Sunny WebBox performs the connection test. The connection test was successful if "OK" is
displayed in the "Result of the last portal connection test" field.
– If the connection test was unsuccessful, refer to Section .10.1 ”General Troubleshooting for