beautypg.com

6 commissioning, 1 before switching on, Commissioning – Lenze EMF2133IB User Manual

Page 31: Before switching on

background image

Commissioning

Before switching on

6

l

31

EDSMF2133IB EN 5.0

6

Commissioning

During commissioning, system−dependent data as e.g. motor parameters, operating
parameters, responses and parameters for fieldbus communication are selected for the
controller.

In Lenze devices, this is done via codes. The codes are stored in numerically ascending order
in the Lenze controllers and in the plugged−in communication/function modules.

In addition to these configuration codes, there are codes for diagnosing and monitoring
the bus devices.

The codes can be set e.g. via an operating module (keypad) or a PC with the Lenze
parameter setting program »Global Drive Control« (GDC).

6.1

Before switching on

(

Stop!

Prior to switching on the mains voltage, check the wiring for completeness,
short−circuit and earth fault.