19. Tower Base
PNEG-707 12', 18', 24' and 30' GSI Commercial Tower Dryer
213
Lower Leg
Lower legs are installed AFTER outside hopper panels are installed.
for placement of lower legs.
Bolt lower leg directly below each upper leg. Use two (2) 5/8" x 2" grade 8 bolts, two (2) 5/8" nuts, and
two (2) 3/4" washers. Insert bolts down, with one (1) washer above and one (1) washer below flange on legs.
Figure 19V Bolting lower leg to upper leg.
Adjust Dryer to Round and Vertical
Dryer must be round at the base and vertical along its entire length.
All 18' dryers are 9"-1" from center to middle of leg. Measure each leg and adjust as necessary to bring
legs into position.
Adjust dryer as required to make entire length of dryer vertical.
IT IS IMPORTANT ENTIRE LENGTH OF DRYER IS VERTICAL.
Vertical is perpendicular to the horizon.
Check by sighting dryer from distance. Also measure with level transit,
surveyor’s level, transom, or plumb line.