beautypg.com

Siemens Automation System S7-400 User Manual

Page 86

background image

Wiring the S7-400

4-26

Automation System S7-400 Hardware and Installation

A5E00850741-01

4.16

Wiring the Front Connector, Spring-Type Terminals

Procedure

To wire the prepared front connector, follow the steps outlined below:

1. Are you using wire end ferrules?

If so: Strip the conductors over 10 mm. Press-fit the wire end ferrules onto the

conductors.
If not: Strip the conductors over 8 to 10 mm.

2. Use a screwdriver (0.5 x 3.5 mm DIN 5264) to release the spring contact of the

first terminal. Start at the bottom of the front connector.
You can release the individual spring contacts at three points: from the front,

from the side or from the back (see Figure 4-15 ).

3. Push the first wire into the released spring contact and withdraw the

screwdriver.

4. Repeat steps 3 and 4 for all other wires.

Releasing

a spring contact

from the front

Releasing

a spring contact

from the side

Releasing

a spring contact

from the back

Figure 4-15 Wiring a Front Connector with Spring-Type Terminals