Commissioning

6-3

Automation System S7-400 Hardware and Installation

A5E00850741-01

6.2

Checks Prior to Switching On for the First Time

Checks Prior to Switching On for the First Time

After installing and wiring your S7-400, it is advisable to check the steps carried out
so far, before switching on for the first time.

Table 6-1 contains a guide in the form of a checklist for your S7-400, and refers to
the chapters containing additional information on the subject.

Table 6-1

Checklist to be Used Before Switching On for the First Time

Points to be Checked

See

Installation

Manual

Chapter

See Reference

Manual

“Module

Specification”

Chapter

See Reference

Manual “CPU

Data” Chapter

Racks

Are the racks secured on the wall, in

the frame or cabinet?

2

Have the necessary clearances been

allowed?

2

Are cable ducts or fan subassemblies

correctly installed?

2

Is the ventilation in order?

2

Grounding and Chassis Ground Concept

Is there a low-impedance connection

(large surface, large-area contact) to

the chassis ground?

2

On all racks, is the connection bet-

ween reference ground and chassis

ground correct (metallic connection or

ungrounded operation?)

4

Are all grounds of the non-isolated

ded modules and the grounds of the

load current power supplies connec-

ted to the reference points?

2

Mounting and Wiring Modules

Are all modules correctly inserted and

screwed on?

2

Are all front connectors correctly wi-

red, plugged into the right modules,

and screwed on?

4

Are any necessary cable ducts or fan

subassemblies fitted correctly?

2