Gradall – Gradall 544D (9136-4003) Service Manual User Manual
Page 351
![background image](/manuals/545357/351/background.png)
9.24
Stage 5
Connect the front top chain devises to the chains and connect the chains to
boom-sections 1 and 2
T
OP,
F
RONT
, C
OMPLETE
B
OOM
A
SSEMBLY
Adjust the 1" retract chain at bottom front to 27/8" for initial set-up.
See Page 9.25
Install the carriage tilt cylinder and connect the hose assemblies to the hydraulic
sub-assembly and the tilt cylinder.
If auxiliary hydraulics are called for, install hoses and electric cable to the nose of
boom-section 4 at this time.
F
RONT,
C
OMPLETE
B
OOM
A
SSEMBLY
The Boom Assembly is complete and ready for assembly to the machine.
Final adjustments should be mode before the machine is returned to service.
GRADALL
GRADALL
1.
2.
3.
4.
➝