beautypg.com

1 anti-islanding enable – KACO Powador XP100-HV User Manual

Page 69

background image

Operating Instructions Powador XP100-HV

Page 69

Parameters

Units

Ranges

Descriptions

Default

IINV Voltage Build
Up Time

msec

0 ~ 9999

The sync of phase between inverter and grid
voltage will be checked after this time, since “Initial
voltage buildup” started (XP-TL does not apply)

100

IINV PLL Stabilization
Time

msec

0 ~ 9999

The phase between inverter and grid voltage
checked and for this time (XP-TL does not apply)

100

IINV PLL P Gain

-

0 ~ 999.99

Grid voltage PLL’s P Gain used for “Initial voltage
buildup” (XP-TL does not apply)

0.2

IINV PLL I Gain

-

0 ~ 999.99

Grid voltage PLL’s I Gain used for “Initial voltage
buildup” (XP-TL does not apply)

0.5

IINV Synchronization
Tolerance

degrees 0 ~ 20

This determines a tolerance limit when synchronize
the inverter and the grid voltage in „Initial voltage
buildup” state (XP-TL does not apply)

10

FRT Overcurrent
Protection Time

msec

0 ~ 5000

The power generation is stopped for this param-
eter value after fault clear in FRT situation

200

Table 17: Controller Parameters

8.7.1 Anti-Islanding

Enable

With activation of Anti-Islanding function, XP100-HV will detect and disconnect itself from the grid within a few
second. If the Anti-Islanding function is not activated, XP100-HV cannot disconnect itself from the grid during
grid failure, and generate power to load independently. For example, when inverter infuse 100 kW power to gird
with 100 kW load connected to PCC(Point of Common Coupling), inverter can generate output voltage indepen-
dently during grid failure, and operate itself with bearing 100 kW load.