beautypg.com

Commissioning 9-15 – Rockwell Automation 1557 MEDIUM VOLTAGE AC DRIVE User Manual

Page 215

background image

COMMISSIONING

9-15

1557-UM050F-EN-P – June 2013

LOGIC POWER SUPPLY TESTS


1. Remove all the gate driver power supply leads, and all power supply connections to the printed circuit

cards.


2. Inspect the low voltage terminal block, measure the 120/240 Volt supply voltages to be sure they are in

limits. Record the voltages.


TEST POINT

EXPECTED VOLTAGE (AC)

MEASURED VOLTAGE (AC)

WIRE NUMBER D60 TO D61

90 TO 132 VOLTS

WIRE NUMBER D-- TO D--

180 TO 264 VOLTS



3. Turn on the low voltage breaker (CB1), this will power up the 50VDC logic power supply. Take the

readings at the DC to DC converter terminal blocks. Record the voltages in the table below:


FUNCTION

TEST POINT

EXPECTED VOLTAGE (DC)

MEASURED VOLTAGE (DC)

TACHOMETER

WIRE NUMBER D59 TO D58

+15

LEMS

WIRE NUMBER D56 TO D57

+24

3%

WIRE NUMBER D55 TO D57

-24

3%

DCB

WIRE NUMBER D54 TO D53

5.1V TO 5.3V

WIRE NUMBER D52 TO D51

+15V ± 3% (1A)

WIRE NUMBER D50 TO D51

- 15V ± 3% (1A)

TRANSDUCERS AND

PRINTER

WIRE NUMBER D48 TO D49

+24

SCANBUS

WIRE NUMBER D46 TO D47

+12

DC POWER INPUT

WIRE NUMBER D44 TO D45

+50