4.4

Protected Meter Proving Data in the AFC's Input Register Bank

The data concerned with Meter Proving is maintained in the Input Register Bank,

(Modbus 3xxxxx read-only Input Register Addresses), protected from change

from outside. There are two areas:

a Latest Prove Results (3x63400 to 3x63709)
b Meter Previous Prove Summary (3x61600 to 3x62399, 50 registers per

meter)


These two areas are described in better detail in the following two topics.

4.4.1 Latest Prove Results

This area contains complete details of the latest prove that has been enabled,

including
Prove setup
Prover and proved-meter configuration summary
Prove state
Prove-level calculations
Run-level input and calculations for each run of the prove

This area supplies almost all the information presented on the proving report (the

remaining info comes from the proved meter’s Previous Prove Summary; see

next). The contents of this area persist until a new prove is enabled, so a proving

report may be regenerated at any time after the prove has been completed and

before the next one is started. There is only one such area for all meters on the

AFC module; therefore enabling a new prove for any meter resets the Prove

Results from the last completed prove, regardless of which meters were involved.