7 final works, 1 preparing the commissioning procedure, Final works – Lenze E94ASHE Axis Single Drive 32-104A User Manual

Page 87: Preparing the commissioning procedure, 7final works

background image

Final works

Preparing the commissioning procedure

7

l

87

EDK94SH104 DE/EN/FR/ES/IT 5.1

7

Final works

7.1

Preparing the commissioning procedure

You need the following for commissioning:

ƒ

Keypad EZAEBK0001

or

ƒ

Computer with Windows® operating system (XP or 2000)

ƒ

Lenze PC software »Engineer«

ƒ

Connection with the controller via an interface, e.g.
– Diagnostic interface X6 with USB diagnostic adapter
– System bus (CANopen)
– Communication module

ƒ

Software manual for the technology application used

ƒ

The communication manual for the network of the automation platform

ƒ

Mains voltage or 24−V voltage supply for the control electronics of the controller

Follow the instructions of the software and/or read the documentation.