3 determining tooling, He guidelines in, Density g cm – INFICON STM-2XM 2-Channel Rate/Thickness Monitor User Manual
Page 130: Tooling (%) tf

7 - 2
PN
07
4-
61
4-
P1
A
STM-2XM Operating Manual
6
Determine the new Density value with
:
[1]
where:
D
1
= Initial Density setting
T
x
= Thickness reading on STM-2XM
T
m
= Measured thickness
7
A quick check of the calculated Density may be made. If the thickness
displayed by STM-2XM has not been zeroed between the test deposition, enter
the calculated Density. Program STM-2XM with the new Density value and
observe whether the displayed thickness is equal to the measured thickness.
NOTE: Due to variations in source distribution and other system factors, it is
recommended that a minimum of three separate evaporations be made, to
obtain an average value for Density.
NOTE: Slight adjustment of Density may be necessary, in order to
achieve T
x
= T
m
.
7.3 Determining Tooling
1
Place a test substrate in the substrate holder of the system.
2
Make a short deposition and determine actual thickness.
3
Calculate Tooling from the relationship shown in
:
[2]
where
T
m
= Actual thickness at substrate holder
T
x
= Thickness reading in STM-2XM
TF
i
= Initial tooling factor
4
Round percent tooling to the nearest 0.1%.
5
When entering this new value for Tooling into the program, if calculations are
done properly, T
m
will equal T
x
.
NOTE: To account for variations in source distribution and other system factors,
obtain an average value for Tooling, using a minimum of three separate
evaporations.
Density g cm
3
D
1
T
x
T
m
-------
=
Tooling (%)
TF
i
T
m
T
x
-------
=