START-UP CHECKLIST

Before energizing the apparatus and Hale FoamLogix system for the first time make sure
the following items are checked:

Electrical

q Tank level sensor(s) wires connected to distribution box and sealed from moisture.

q Tank level sensor(s) function properly.

q Control cable connection at distribution box correct and tight.

q Flowsensor cable properly connected to control unit.

q All cables and wires are secured and protected from damage during operation.

q Control and flowsensor cables properly folded and secured; radio antennas, power

lines and equipment away from cables.

q Foam Pump and motor assembly properly grounded using flat ground strap.

q Correct voltage provided. Direct current, negative ground.

q Adequate current, 60 AMPS minimum, available. Main power direct to battery, battery

switch or solenoid without primer or other accessories tied in.

q Primary electrical and ground connections tight and protected from corrosion with

silicone sealant.

q Splices in wires sealed from moisture using adhesive filled heat shrink tubing.

q Hale FoamLogix system ON/OFF switch on the distribution box is in the ON position.

q If installed, ADT, MST or MDT

ΙΙ

electrical connections correct.

q If installed, Remote ON/OFF switch cable connection correct.

Liquid

q Flowsensor mounted with flow arrow in the correct direction for water flow.

q Check valves are properly mounted in water and foam concentrate lines.

q Strainer mounted for proper concentrate flow direction in foam tank to pump hose.

q Foam tank to foam pump valve is in place and open.

q Check valve/injector fitting lines are proper size and connections are tight.

q BYPASS valve is properly mounted and oriented for direction of concentrate flow.

q Foam concentrate gravity feeds to foam pump from foam concentrate tank.

q All hoses free of kinks and sharp bends.

q No sharp bends that can trap air exist in system.

q MST positioned to FOAM TANK or MDT

ΙΙ

positioned to TANK A.

q Flush water connections correct and tight.

q Discharge piping hydro tested in accordance with NFPA/UL requirements.

q Bypass valve handle is in the INJECT position.

Foam Pump

q Foam pump and motor assembly mounted in horizontal position with base plate down.

q Foam pump and motor assembly properly secured using proper mounting hardware.

q Foam pump suction and discharge hoses connected to proper ports.

q Foam pump suction and discharge hose fittings tight.

Optional ADT

q Panel placard mounted on operator panel.

q Air hoses connected and connections tight.

q Selector switch is in the TANK A position.

q Bypass handle is in the INJECT position.