15  Commissioning

Installation Manual

SCCP-JP-IA-A4-en-12

77

15.8 Switching On the Voltage Supply and the AC Circuit Breaker

1. Close the measurement and disconnect terminals.

2. Switch the circuit breaker of the grid monitoring on.

☑ The electronic components of the Sunny Central switch on.
☑ The fans switch on and start drawing air in through the air

intake vents.

✖ The fans do not switch on?

• Contact the SMA Service Line.

3. Switch the AC circuit breaker on.

4. Switch the supply voltage circuit breaker on.