7  Transporting the Sunny Central

SMA Solar Technology AG

30

SCCP-JP-IA-A4-en-12

Installation Manual

7.4 Transporting the Sunny Central Using a Crane Fork

Requirements:

☐ The crane and crane fork must be designed to take the weight of the Sunny Central of 1,800 kg.
☐ The crane fork must be properly coupled to the crane.
☐ All kick plates must be removed.

Procedure:

1. Position the forks of the crane fork underneath the Sunny Central

from the front or rear. Take the center of gravity of the

Sunny Central into account and move the crane fork right under

the Sunny Central.

2. Slowly raise the crane fork with the Sunny Central.
3. Transport the Sunny Central to the mounting location and set down on a suitable surface.

7.5 Transporting the Sunny Central Using a Forklift

Requirements:

☐ The forklift must be designed to take the weight of the Sunny Central.
☐ All kick plates must be removed.

:$51,1*

Danger of crushing if the Sunny Central tips over
With the kick plates mounted at the rear of the Sunny Central, the supporting surface of the Sunny Central on the forks

of the crane fork is inadequate. Vibrations during transport may cause the Sunny Central to slip off the crane fork and

tip over. This can result in death or serious injury.

• When the kick plates are mounted, always stabilize the Sunny Central with crane slings or steel chains during

transport.

:$51,1*

Danger of crushing if the Sunny Central tips over
With the kick plates mounted at the rear of the Sunny Central, the supporting surface of the Sunny Central on the forks

of the forklift is inadequate. Vibrations during transport may cause the Sunny Central to slip off the forklift and tip over.

This can result in death or serious injury.

• When the kick plates are mounted, always stabilize the Sunny Central with crane slings or steel chains during

transport.