7  Transporting the Sunny Central

Installation Manual

SCCP-JP-IA-A4-en-12

31

Procedure:

1. Position the forklift under the Sunny Central either from the front or

the rear. Take the center of gravity of the Sunny Central into

account and move the forklift truck right under the Sunny Central.

2. Stabilize the Sunny Central using e.g. tension belts.
3. Slightly raise the Sunny Central.
4. Transport the Sunny Central to the mounting location and set down on a suitable surface.

7.6 Transporting the Sunny Central Using a Pallet Truck

Requirements:

☐ The pallet truck must be designed to take the weight of the Sunny Central.
☐ All kick plates must be removed.

Procedure:

1. If the Sunny Central is to be transported on a wooden pallet, move

the pallet truck under the Sunny Central from the front or the rear.

2. If the Sunny Central is to be transported without a wooden pallet,

the pallet truck must always be moved under the Sunny Central

from the side. Ensure that the side panels of the Sunny Central are

not damaged by the forks.

3. Slightly raise the Sunny Central.
4. Transport the Sunny Central to the mounting location and set

down on a suitable surface.