6 preparation for installation, 1 selecting a mounting location, 1 requirements for the mounting location – SMA SC 500CP-10-JP Installation Manual User Manual
Page 20: 2 dimensions of a sunny central
6 Preparation for Installation
SMA Solar Technology AG
20
SCCP-JP-IA-A4-en-12
Installation Manual
6 Preparation for Installation
6.1 Selecting a Mounting Location
6.1.1 Requirements for the Mounting Location
Requirements:
☐ If the Sunny Central is to be installed in an electrical equipment room, an adequate supply of fresh air must be
ensured. If this is not the case, an additional ventilation system must be installed, e.g an external fan.
☐ The mounting location must be freely accessible at all times.
☐ The mounting location must be below the maximum installation altitude (see Section 17 "Technical Data", page 80).
☐ The ambient temperature must be within the operating temperature range (see Section 17 "Technical Data",
☐ The mounting location must meet the requirements on ambient conditions (see the Technical Information "Installation
Requirements - Important Information on Transportation and Installation for Sunny Central 500CP-JP/630CP-JP/
800CP-JP").
6.1.2 Dimensions of a Sunny Central
Dimensions of a Sunny Central for Outdoor Installation
Figure 5: Dimensions with roof
Orientation of the inverter for protection against noise
The front side of the inverter with the supply air opening is louder during operation than the rear side. Especially in
residential areas, the inverter should be oriented with the rear side facing the residential area.