8 installing the sunny central, 1 attaching the sunny central without base, 2 installing the sunny central on a base – SMA SC 500CP-10-JP Installation Manual User Manual
Page 36

8 Installing the Sunny Central
SMA Solar Technology AG
36
SCCP-JP-IA-A4-en-12
Installation Manual
8 Installing the Sunny Central
Depending on the order option , the Sunny Central can be installed directly on the foundation without a base or attached
to a base. You must select the relevant section.
8.1 Attaching the Sunny Central without Base
Once the Sunny Central has been aligned on the foundation, you can attach it to the foundation using concrete screw
anchors and screws.
Requirements:
☐ The mounting surface must be prepared for installation (see Section 6.2 "Preparation for Mounting without Base",
☐ The Sunny Central must be taken off the Euro pallet.
Additionally required material (not included in the scope of delivery):
☐ 4 suitable concrete screw anchors
Procedure:
• Insert the concrete screw anchors through the brackets of the Sunny Central in the foundation. The exact procedure
depends on the type of screw anchors used.
8.2 Installing the Sunny Central on a Base
Once the Sunny Central has been aligned on the base, you can attach it to the base with screws. The screws for attaching
the inverter to the base are included in the scope of delivery of the base.
Requirements:
☐ The base must be prepared for installation (see Section 6.3 "Preparation for Mounting on a Base", page 28).
☐ The Sunny Central must be taken off the Euro pallet.
Procedure:
• Insert the screws through the brackets on the Sunny Central in the base and screw tight.