15  Commissioning

SMA Solar Technology AG

72

SCCP-JP-IA-A4-en-12

Installation Manual

15 Commissioning

15.1 Sequence of Commissioning

'$1*(5

Danger to life from electric shock due to live voltage
High voltages are present in the live components of the Sunny Central. Touching live components results in death or

serious injury due to electric shock.

• When working in a high contact-risk environment, wear personal protective equipment.
• Do not touch any live components.
• Follow the instructions precisely.
• Observe all warning messages on the product and in the documentation.
• Observe all safety precautions of the module manufacturer.
• Provided live voltage is not absolutely necessary, always disconnect the following components from voltage

sources before performing any work on the inverter:

– Grid voltage for grid feed-in
– Internal power supply
– DC voltage from the PV array
– Additional external voltages, e.g. control signals from a control room

• Ensure that no disconnected components can be reconnected.
• Wait 15 minutes after switching off the inverter before opening it. This will ensure that the capacitors are

discharged.

• Before working on the Sunny Central, check that all devices are completely voltage-free.
• Ground and short-circuit.
• Cover or isolate any adjacent live components.

Warranty claims
Warranty claims can only be made valid if commissioning was carried out by SMA Solar Technology AG or if the

fully completed and signed "Commissioning Report for Sunny Central Systems" is available at SMA Solar

Technology AG.

Connecting and disconnecting the AC voltage of the MV transformer
Only a duly authorized person trained in electrical safety is allowed to connect and disconnect the AC voltage of

the MV transformer.

Procedure

See Section

1.

Check the Sunny Central cabling

15.2, page 73

2.

Insert fuses or disconnection blades

15.3, page 73

3.

Mount the protective covers

15.4, page 74

4.

Commission the DC sub-distribution, e.g. Sunny String-Monitor

DC sub-distribution

documentation

5.

If applicable, commission the DC main distribution, e.g. Sunny Main Box.

DC main distribution

documentation

6.

Check the DC voltages

15.5.1, page 74