beautypg.com

2 transporting the sunny central using a crane, 3 mounting the roof of the sunny central – SMA SC 500CP-10-JP Installation Manual User Manual

Page 34

background image

7  Transporting the Sunny Central

SMA Solar Technology AG

34

SCCP-JP-IA-A4-en-12

Installation Manual

7.7.2 Transporting the Sunny Central Using a Crane

Requirements:

☐ The crane and hoist must be designed to take the weight of the Sunny Central.
☐ The hoist must be properly connected to the crane.
☐ The roof of the Sunny Central must be dismantled.

Procedure:

1. Attach the hoist to all four lifting eyes in the Sunny Central.
2. Raise the crane hook slowly until the hoist is taut.

3. Ensure that the hoist is attached correctly.
4. Slightly raise the Sunny Central.
5. Transport the Sunny Central as close to the ground as possible.
6. Transport the Sunny Central to the mounting location and set down on a suitable surface.

7.7.3 Mounting the Roof of the Sunny Central

Procedure:

1. Position the roof on the Sunny Central.
2. Tighten the grounding conductor on the Sunny Central

(torque: 14.2 Nm).

&$87,21

Danger of crushing due to heavy, unwieldy roof
The roof of the Sunny Central is unwieldy and weighs 30 kg. If you try to move the roof on your own, you run a risk of

having limbs crushed.

• Only move the roof with at least two persons.