Commissioning

Switch−on sequence

7

l

39

LDEDS−CCU210B EN 4.0

7.2

Switch−on sequence

)

Note!

ƒ

Disconnect the control system from the mains before you attach or remove
the external EXMID1 data memory!

ƒ

If the external EXMID1 data memory is attached or removed during voltage
is applied, the data saved on it can be damaged:
– If data are damaged, the control system reports the error F008.

^ 81

)

Note!

ƒ

Carefully follow the switch−on sequence described.

ƒ

In case of faults during commissioning, the chapter "Troubleshooting and
fault elimination" (

^ 78) will help you.

How to switch on the control system:

1. If the control system is equipped with an external EXMID1 data memory:

– Connect the external EXMID1 data memory to plug X50.

2. Switch on the mains:

– After approx. 1 s the control system is ready for operation.

3. The control system behaves according to the specifications parameterised (signals

on the digital inputs):

A The control system is ready for operation if the display shows the status display 00

or the current operating status.

B The control system is not ready for operation if the signal in the display is blinking:

– A fault is active.
– Eliminate the fault. (

78)