• Finishing Calibration

Set the next calibration due date.

1.

Carry out the procedure below to show the display.

Press

MENU (to switch to setting mode) > Set Calibration tab > Finish

Calibration.

A window for setting the calibration due date appears.

2.

Set the next calibration due date, and press

DISP/ENTER.

Soft Key

Description

Input

Enter the date directly.

+1 Week

Set the date by adding weeks to the current calibration due date.

–1 Week

Set the date by subtracting weeks from the current calibration due date.

+1 Month

Set the date by adding months to the current calibration due date.

–1 Month

Set the date by subtracting months from the current calibration due date.

3.

Use the

arrow keys to select Execute, and press DISP/ENTER.

Calibration is complete.

Note

• You cannot set the calibration due date to a date before the current day.
• Whenever you complete calibration, a log is added to the login log (the operation log on DXs

with the /AS1 option).

3.13 Managing the Input Calibration Interval (/CC1 option; release numbers 4 and later)