beautypg.com

Step 7: verification & readiness check – Grass Valley iControlEdge v.1.20 Installation User Manual

Page 58

background image

54

Installation & Setup

33

14. On the Network page, type the Application Server’s IP address in the Destination host box. Type the

appropriate port number in the Destination port base box (this number must match what is specified
in the

ALLEGRO.sdp

file for this Allégro frame):

15. Click Apply.

16. Restart the Allégro.

17. Repeat steps step 11 to step 16 for each Allégro in the iControl Edge configuration.

18. Restart iControl on the Application Server.

Step 7: Verification & Readiness Check

When you finish configuring all devices, use an SSH client such as PuTTY to ping them from the Application
Server to make sure that the devices recognize each other on your network.

To verify that all devices are properly connected to your system:

1. Launch PuTTY and log on to the Application Server (see “Establishing an SSH Connection with an

Application Server” on page 94).

2. In the PuTTY command line window, type the following:

ping -s 32 AAA.BBB.CCC.DDD

where

AAA.BBB.CCC.DDD

is the new IP address of a Global Caché GC-100 Network Adapter. A series

of messages similar to the following should appear:

PING 10.10.120.50 (10.10.120.50) 32(60) bytes of data.
40 bytes from 10.10.120.50: icmp_seq=1 ttl=99 time=3.43 ms

Note: PuTTY is available from your Application Server’s Useful Downloads page. If you do not
have PuTTY installed on your PC or laptop, see “Using PuTTY” on page 93.

IP address of the

Application Server

Port number must match what is
specified in the corresponding
SDP file on the Application Server