Appendix d: voltage calibration operation – FeiYu Tech FY-Panda2 Autopilot User Manual

Page 58

background image

Guilin Feiyu Electronic Technology Co., Ltd.

Guilin Feiyu Electronic Technology Co., Ltd http://www.feiyu-tech.com [email protected]

Page 55

Map making success should be generate 3 format files with the same name,

(

“.gst”, “.tab”, “.jpeg” files). The .gst file is the map file that load in the 2D

view on the GCS, after load it can do route planning or other operations.

The region have selected too large or too small may cause failure of the map

making. Total number of the pictures should be less than 512 pictures.

The screenshot resolution of the map making about the GCS is

“Height”, In

the same conditions, the higher the resolution, the clearer map which make in

3D view.

Appendix D: Voltage Calibration Operation

( 1 ) Measure the actual voltage of the batteries, record as:V0.

( 2 ) Connect the batteries to the power manager

,the voltage display on the

GCS(BAT1) record as V1 .

Formula for voltage calibration ratio

:C=(V0 / V1) x 100

For example: Actual voltage of the batteries V0 =15.76 V ;

Voltage display on the GCS V1=15.5 V

Voltage Ratio C=(15.74/15.5) x 100=1.017*100=102

Settings of voltage calibration:

―Menu‖

——― Autopilot setting ‖—— ―Power Voltage

Calibration

‖, it will pop-up the setting dialog.

“Voltage Ratio”= “0” means that the voltage display without calibration. If the

voltage is need to be correct, please calculate the voltage ratio "C".

According to the above steps

,then enter into the dialog , click on“OK”button to

confirm the setting of this parameter (For example: 102).