CHAPTER 2: INSTALLATION

PR2: 05/09/12 Page

17 of 152

Benchmark 1.5LN Low NOx Boiler

Operation and Maintenance Manual

OMM-0041_0D

GF-120

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913 • Ph: 800-526-0288

NOTE

There are two slightly different types of condensate traps that may

be used in your configuration; an older style without built-in

adapter, and a newer style with a built-in adapter (see Figure 2-5).

Installation is the same (1/4” threads are inside built-in adapter on

newer style).

Refer to Figure 2-5 and install the trap as follows:

1. Install 3/4” NPT nipples in the tapped inlet and outlet of the condensate trap (part no.

24060).

2. Install a third 3/4” NPT nipple in the tapped condensate outlet of the exhaust manifold.

3. Connect the exhaust manifold nipple to the condensate trap inlet using a female union.

4. install a suitable support under the condensate trap and ensure that the trap is level.

5. Connect a length of 1” I.D. polypropylene hose (part no. 91030) to the nipple on the

outlet side of the condensate trap and secure it with a hose clamp.

6. Route the hose on the trap outlet to a nearby floor drain.

If a floor drain is not available, a condensate pump can be used to remove the condensate to

drain. The maximum condensate flow rate is 20

GPH. The condensate drain trap, associated

fittings and drain lines must be removable for routine maintenance.

Figure 2-5: Condensate Trap Installation: Older (left) and Newer (right) Style

2.7 GAS SUPPLY PIPING

The AERCO Benchmark 1.5 Gas Components and Supply Design Guide, GF-4030 must be

consulted prior to designing or installing any gas supply piping.

WARNING

NEVER USE MATCHES, CANDLES, FLAMES OR OTHER

SOURCES OF IGNITION TO CHECK FOR GAS LEAKS.

Many soaps used for gas pipe leak testing are corrosive to metals.

There-fore, piping must be rinsed thoroughly with clean water after

leak checks have been completed.