2 setting the unit, Benchmark 1.5ln low nox boiler, Gf-120 – AERCO BMK 1.5 LN July 2011 User Manual
Page 15
CHAPTER 2: INSTALLATION
PR2: 05/09/12 Page
15 of 152
Benchmark 1.5LN Low NOx Boiler
Operation and Maintenance Manual
OMM-0041_0D
GF-120
AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913 • Ph: 800-526-0288
Setting the Unit
2.4.2
The unit must be installed on a 4 inch to 6 inch housekeeping pad to ensure proper condensate
drainage. If anchoring the unit, refer to the dimensional drawings in Appendix F for anchor
locations. Two lifting tabs are provided at the top of the heat exchanger. Figure 2-2 shows the
location of the tab on the top-left side. The second tab is located on the top-right side of the heat
exchanger. USE THESE TWO TABS TO LIFT AND MOVE THE UNIT. Remove the top panel
from the unit to provide access to the lifting tabs. Remove the four (4) lag screws securing the
unit to the shipping skid. Lift the unit off the shipping skid and position it on the 4 inch to 6 inch
housekeeping concrete pad (required) in the desired location.
WARNING
WHEN LIFTING OR MOVING THE BOILER:
•
DO NOT MANIPULATE THE BOILER USING THE GAS TRAIN OR
BLOWER
•
WHEN USING THE LIFTING TABS, ENSURE THERE IS NO LOAD
PLACED ON THE GAS TRAIN OR BLOWER
Figure 2-2: Partial Top View Showing Lifting Tab Location
In multiple unit installations, it is important to plan the position of each unit in advance. Sufficient
space for piping connections and future service/maintenance requirements must also be taken
into consideration. All piping must include ample provisions for expansion
.
If installing a Combination Control Panel (CCP) system, it is important to identify the
Combination Mode Boilers in advance and place them in the proper physical location. Refer to
Chapter 5 for information on Combination Mode Boilers.