beautypg.com

2 test after machine modification, 3 regular inspection, 7commissioning – Pilz PSENvip RL D P User Manual

Page 103: 5 check protective equipment

background image

7.5

Check protective equipment

7

Commissioning

Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
Telephone: +49 711 3409-0, Telefax: +49 711 3409-133, E-Mail: [email protected]

7-22

press brake must be fully configured with the upper tool (maximum
weight). The test should be performed at maximum closing speed.

7.5.1.2

Test after machine modification

Test after machine modification

7-

Inbetriebnahme_Schutzeinrichtung_pruefen_Funjktionspruefung_Aenderung

The safeguards should be tested after each machine modification (e.g.
after entering the overrun, after a tool change, after changes to the press
controller). The tests should be the same as those carried out during in-
itial commissioning.

Changing the PSENvip or swapping PSENvip components should also
be regarded as a modification.

You must comply with the requirements of the applicable national regu-
lations.

7.5.1.3

Regular inspection

Regular inspection

7-

Inbetriebnahme_Schutzeinrichtung_pruefen_Funjktionspruefung_regelmaessig

Safeguards must undergo a regular function test:

After switching on the supply voltage for the first press stroke

At least every 30 hours

INFORMATION
The test during initial commissioning may only be carried out by
qualified personnel.

INFORMATION
The check following modifications may only be carried out by
qualified personnel.

NOTICE
The safety-related control system must request these regular
inspections of the safeguard via a user program.

INFORMATION
Trained operators must be used for the daily check.