45 • Connecting Instruments to the PC Controller Program

4.

Turn on each SDM-2012 by pressing and holding the SDM-2012’s POWER
button. When the control panel LEDs turn on, release the POWER button.

5.

The BUMP

T

and CAL

S

LEDs will turn off and the COPY LED will be

steadily on or off. It will be on if the SDM-2012 was used in Standalone
Configuration and calibration and bump test records are still stored in the
SDM-2012’s memory (see the SDM-2012 Docking Station Standalone
Configuration Manual for more information). The CHARGE LED will be
blinking green if the SDM-2012 is operating properly or solid red if there is a
system failure.

6.

When a connection has been established between the SDM-GX Docking
Station PC Controller Program and all of the SDM-2012s, the main program
window will appear as shown below.

Figure 32: SDM-2012 Connection

7.

Connect the gas out to instrument line of each SDM-2012 to the inlet of each
instrument.