Figure 111. Securing the Power Cord for the AT-SBxPWRSYS1 AC Power
Supply to an Anchor
4. Connect the power cord to an appropriate AC power source to power
on the power supply.
5. If the chassis has two AT-SBxPWRSYS1 AC System Power Supplies,
repeat this procedure to power on the second power supply.
After powering on the AT-SBxPWRSYS1 AC System Power Supplies, do
one of the follow:
If the chassis has AT-SBxPWRPOE1 PoE Power Supplies,
perform the procedure in “Powering On the AT-SBxPWRPOE1
Power Supply” on page 174.
Otherwise, go to “Monitoring the Initialization Process” on
page 203.