Setting up rack to mount
Procedure 1 Setting up rack to mount
At the rack,
1
Mount all equipment on the rack: Refer to following diagram that
displays the mounting for the rack.
•
Mount Layer-2 switch.
•
Mount MRV terminal server.
•
Mount Sun Fire V100s.
— Management/Accounting server
— Database server
— Application server
— IPCMProvWCM server
•
(optional equipment) Mount conference server. Refer to the
Media Application Server documentation for more
information.
•
(optional equipment) Mount gateway. Refer to
customer-specific gateway installation documentation.