8  Commissioning

SMA Solar Technology AG

66

SI30M-44M-60H-80H-IA-en-30

Installation Manual

10. Switch off the Sunny Island and open the BatFuse load-break

switch quickly.

11. Connect BatCur+ measuring conductor on the side for connecting

the BatFuse.

12. Connect the BatCur– measuring conductor on the side for

connecting the battery.

13. Close the BatFuse load-break switch quickly and switch on the Sunny Island.

8.1.5 Setting the Functions of the Multifunction Relays

Note the function of the multifunction relays in the following table during the electrical connection (see Section 7.4,

page 27). Alternatively, the parameter directory can be used (for parameter directory in menu 240# Relay, see the

Sunny Island inverter operating manual). The multifunction relays of the master are preset in battery backup systems and

cannot be changed.

Table for configuration:

Multifunction relay

Value

Function/output

Relay 1 of Sunny Island inverter/

master, parameter 241.01 Rly1Op
Relay 2
of Sunny Island inverter/

master, parameter 241.02 Rly2Op
Relay 1
of slave 1, parameter

244.01 Rly1OpSlv1
Relay 2
of slave 1, parameter

244.02 Rly2OpSlv1
Relay 1
of slave 2, parameter

245.01 Rly1OpSlv2
Relay 2
of slave 2, parameter

245.02 Rly2OpSlv2