7  Electrical Connection

Installation Manual

SI30M-44M-60H-80H-IA-en-30

35

Requirements:

☐ The total length of the communication bus must not exceed 30 m. Keep in mind that the communication bus possibly

connects several nodes such as other Sunny Island Chargers.

Procedure:

1. Plug the data cable into a free pin connector ComSync on the

Sunny Island. Ensure that the cable is correctly connected (see

Section 7.5.4 "Connecting the Data Cable", page 54).

2. Ensure that the communication bus is closed at each end, e.g. with a terminator.

7.4.7.5 Connecting the Data Cable of the Sunny Island Charger 50 Charge

Controller

A maximum of four Sunny Island Charger 50 devices can be connected per cluster (see the Quick Reference

Guide "Off-Grid Systems").

Requirements:

☐ The total length of the communication bus must not exceed 30 m. Keep in mind that the communication bus possibly

connects several nodes such as additional Sunny Island inverters.

Cable requirements:

☐ Classification: CAT5e
☐ Type of plug: RJ45

Procedure:

1. Plug the data cable into a free pin connector ComSync on the

Sunny Island. Ensure that the cable is correctly connected

(see Section 7.5.4 "Connecting the Data Cable", page 54).

2. Connect the other end of the data cable to one Sunny Island Charger 50 and further Sunny Island Charger 50

devices to one another (see documentation for the Sunny Island Charger 50 charge controller).

3. Ensure that the communication bus is closed at each end, e.g. with a terminator.