7.6 Checking the Wiring

Ensure that you carry out all tests relevant to the system and rectify all detected problems. Tip: Tests can be documented

directly in the tables. Cross out all tests not applicable.

Requirement:

☐ All Sunny Island inverters must be voltage-free (see the Sunny Island inverter operating manual).

Procedure:

Checking the grounding

Checking the additional grounding

If the battery is grounded, you must check the additional grounding on the Sunny Island.

Test point

Test criterion

OK

Enclosure opening, grounding conductor/

ExtVtg

Enclosure opening is sealed with a filler plug or M20 cable gland.

The cable diameter of the cable must be 7 mm to 14 mm for an

M20 cable gland.

Conductor cross-section of the grounding

conductor at the AC1 and AC2

connections

If one grounding conductor is connected, the conductor

cross-section must be at least 10 mm². If two grounding conductors

are connected, the cross-section of each conductor must be at least

4 mm².

Grounding conductor connection to

ground

The grounding conductor must be grounded, e.g. by connection to

a grounding busbar or a foundation ground electrode.

With a TN system, neutral conductor and

grounding conductor connection

Ensure by measuring that there is a conductive connection between

the neutral conductor and the grounding conductor.

Grounding of the battery

Ensure that the battery is not grounded unintentionally.
If the battery has been grounded intentionally, ensure that the

conductor cross-section is sufficient (see Section 7.3 "Connecting

the Grounding Conductor in Systems With Grounded Battery",

page 25).

Test point

Test criterion

OK

Conductor cross-section for the additional

grounding

The conductor cross-section must correspond to the grounding of

the battery.

Connection of additional grounding

Hexagon socket screw is screwed tight (torque: 4 Nm to 5.7 Nm).

Grounding conductor connection to

ground

The grounding conductors must be grounded, e.g. by connection to

a grounding busbar or foundation ground electrode.