7. Initial Installation

7 - 1

Planning and Installation - Rev. 3 / 04.2005

7.

INITIAL INSTALLATION

WARNING

The control panels and mainframe do not contain any control elements or

switches required for operation of the switcher. For this reason, the control

panel should not be opened by unauthorized persons and should always be

locked.

The panel must be opened by authorized service personnel only!

Prior to opening the panel make sure that there are no objects on the panel,

such as pens, screwdrivers or other tools. When opening the panel, they

might fall into the device and cause disturbances.

7.1

INSTALLATION CHECKLIST

NOTE!

The installation checklist comprises the procedures for installation and ini-

tial installation described in this manual. It is recommended to install the de-

vices with the aid of the instructions below.

Please note that the line voltage is only applied when you are expressively

requested in the checklist to do so.

D

After having thoroughly unpacked the equipment and checked the packings for
mains cables and other small parts, check the delivery with regard to damages

caused by transport. If you note a damage, immediately inform the forwarding

agent.

Using the packing slip make sure that the delivery is complete.

D

Before starting installation, read the enclosed installation instructions and be-
come familiar with the safety instructions.

D

Mount the control panel into a desk.

D

Mount the mainframe into an equipment cabinet.

D

Check the plug-in cards in the mainframe with regard to correct position in the
support frame and make sure that the plug-in cards are locked.

D

Check and set the switches and jumpers to the required operating position.

D

Establish the earth connection.

D

Make sure that the line voltage is conform with the voltage adjusted in the deliv-
ered equipment. If required, change it over to the corresponding line voltage.

Mainframe:

100 or 200 - 240 V AC

Panel:

90 - 264 V AC

D

Set the service power switch on control panel and mainframe to position ON.

D

Establish Cheapernet cabling between control panel and E-box. Connect the
video input and output cables as well as the other control cables.