Holiday Start/Stop Day Selection
From the Unit Schedule Menu, select Holiday Schedules. The following
four screens will appear in order:
Hldy
Holiday # 1
Start Mon/Day.: XXXX
[ July 4
th
= 704 ]
Hldy
Holiday # 1
Stop Mon/Day.: XXXX
[ July 5
th
= 705 ]
The screens will step through the fourteen possible holidays, one period
at a time. Line 2 shows which holiday is currently being programmed.
Since a holiday period can encompass more than one day, you need to
program the day the holiday starts and the day the holiday ends. If your
holiday only lasts one day, simply set both the Start Day and the Stop
Day to the same value. Remember to combine the month and day into
a single four-digit value.
EXAMPLE:
704 = July 4
th
(
NOTE:
Leading zero not required)
1225
=
December
25
th
Holiday Start/Stop Times
Hldy
Holiday Schedule
Start Event #1: XXXX
Stop Event #1: XXXX
Hldy
Holiday Schedule
Start Event #2: XXXX
Stop Event #2: XXXX
The fourteen holidays all use the same Start and Stop times which you
program on this screen and the next. You must enter the time in 24-hour
military format, the same as a regular week schedule.
Normally, the holidays will operate in an unoccupied mode or a reduced
schedule mode. There are two start/stop events available on holidays to
match the standard schedule number of events.
Holiday Scheduling and Schedule Override
Schedule Override
From the Unit Schedule Menu, select Schedule Override. The following
screen will appear:
Ovrd
Schedule Override
Enter Override...: X
[0=Auto 1=ON 2=OFF]
If you want to force the unit to operate in a continuous Occupied or
Unoccupied mode, select this menu item to activate the desired method.
If a Schedule Override is active, all other methods of schedule control
are ignored (Push-Button, Internal, and Remote).
As you can see on the last line of the display, enter
<1>
to run continu-
ously in the Occupied Mode or
<2>
to run continuously in the Unoc-
cupied Mode. To restore normal schedule operations, enter
<0>
.
This override remains in effect until canceled and does not time-out
like the Output Overrides do after 10 minutes of no communications.
NOTE: Do not use the Force OFF mode in place of setting
all the week schedules to ZERO if you are using a
Remote Signal for your scheduling since the Override
has priority over the Remote Signal.