95

(4) Example of program start signal (rise) ON and (fall) OFF timing

Q

Q

Q

Q Example of program start signal rise (ON) timing

The figure below shows how to make the program start signal rise with
robot system outputs (external mode output and single-cycle end
output).

Robot status

Wait for start

Single-cycle
operation

Next cycle
operation

External mode

ON

(output)

OFF

1-cycle end

ON

(output)

OFF

Program start

ON (shorted)

signal (input)

OFF (open)

200 ms. or
more required

Example of Program Start Signal Rise Timing

Caution: The program start signal for the first cycle rises as soon as

the external mode becomes valid and the conditions of the
peripheral devices are met. The program start signal for
subsequent cycles rises after output of a single-cycle end
signal.