SECTION 3
ISLANDER PLUS INSTALLATION PROCEDURES
3-1.
GENERAL
This section provides the installation procedures for the Islander PLUS.
These procedures include:
• Islander PLUS Pedestal installation
• Wiring
• Post installation check.
3-2.
INSTALLATION SPECIFICATIONS
3-2.1. General
NOTE
Perform a site survey of the station prior to
installation
Installation procedures and requirements depend, to some extent, on the specific fuel dispenser
models and the site layout. Therefore, use the information in this section to develop installation
plans for each specific installation. Since installation requirements vary widely from case to case,
no installation hardware is supplied by the equipment manufacturer, and installation planners must
develop their own requirements.
The customer should provide an installation plan, designed by an authorized engineer. This plan
design should reflect the existing electric infrastructure of the site.
3-2.2. Precautions and Safety Notes
Prior to actual installation activities, carefully observe the precautions and safety notes detailed in
paragraphs 2-2.2 and 2-4.2, and at the opening pages.