CHAPTER 6 – MAINTENANCE

OMM-0078_0L

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

Page 79 of

206

GF-128

Phone: 800-526-0288

PRI: 11/25/2014

Igniter-Injector

Inspection/Replacement – Continued

7.

Prior to reinstalling the igniter-injector, apply a high temperature, conductive, anti-seize
compound to the threads.

NOTE

The igniter-injector replacement kit (P/N 58023) includes three clocking
(indexing) washers, which are used, as needed, so that when the igniter-
injector is fastened in place, the gas injector tube is pointing outward, toward
the intake manifold perimeter.

8.

Refer to Figure 6-2 and reinstall the igniter-injector on the intake manifold flange. Install one
to three clocking washers, as needed, to position the igniter-injector’s gas tube so that it is
pointing outward, toward the outer-edge of the intake manifold flange. Torque to 15 ft-lbs.
Do not over tighten.

VIEWED FROM BELOW, LOOKING UP

Figure 6-2. Igniter-Injector & Flame Detector Mounting Details

9.

Connect the ignition assembly to the gas injector tube of the igniter-injector by securing the
compression nut to the elbow of the ignition assembly.

10.

Reconnect the igniter-injector cable and ground wire.

11.

Reinstall the side and rear panels on the unit.



120°

ANGLE OF GAS

INJECTOR

TUBE

FLAME

DETECTOR

TERMINAL

IGNITER-
INJECTOR

FLAME
OBSERVATION
PORT