7.
Prior to reinstalling the igniter-injector, apply a high temperature, conductive, anti-seize
compound to the threads.
NOTE
The igniter-injector replacement kit (P/N 58023) includes three clocking
(indexing) washers, which are used, as needed, so that when the igniter-
injector is fastened in place, the gas injector tube is pointing outward, toward
the intake manifold perimeter.
8.
Refer to Figure 6-2 and reinstall the igniter-injector on the intake manifold flange. Install one
to three clocking washers, as needed, to position the igniter-injector’s gas tube so that it is
pointing outward, toward the outer-edge of the intake manifold flange. Torque to 15 ft-lbs.
Do not over tighten.
VIEWED FROM BELOW, LOOKING UP
Figure 6-2. Igniter-Injector & Flame Detector Mounting Details
9.
Connect the ignition assembly to the gas injector tube of the igniter-injector by securing the
compression nut to the elbow of the ignition assembly.
10.
Reconnect the igniter-injector cable and ground wire.
11.
Reinstall the side and rear panels on the unit.
120°
ANGLE OF GAS
INJECTOR
TUBE
FLAME
DETECTOR
TERMINAL
IGNITER-
INJECTOR
FLAME
OBSERVATION
PORT