Welch Allyn Acuity LT Mobile - Installation Guide User Manual
Page 39

Installation Guide
Chapter 4 Install the system
35
14.
a. Unplug UPS 1 (in the equipment closet) from AC power
b. Confirm that the Acuity LT Central Station display shows
patient data with no yellow alert messages.
The UPS might emit an audible alarm.
c.
Plug UPS 1 into AC power.
Pass
Fail
14a.
For systems with 4-7 APs only:
a. Unplug the additional UPS (in the equipment closet) from AC
power
b. Confirm that the Acuity LT Central Station display shows
patient data with no yellow alert messages.
The UPS might emit an audible alarm.
c.
Plug in the UPS to AC power.
Pass
Fail
15.
a. Unplug UPS 2 (at the nurses station) from AC power
b. Confirm that the Acuity LT Central Station display shows
patient data with no yellow alert messages.
The UPS might emit an audible alarm.
c.
Plug in UPS 2 to AC power.
Pass
Fail
16.
a. To check the modem, call Welch Allyn Technical Support
(1-800-289-2501 or +1 503-530-7500).
b. Provide the telephone number of the modem, and ask the
technician to check the modem operation.
Pass
Fail
17.
Measure the RSSI for your facility as described on
signal strength indication (RSSI) check”
on page 36 and complete
the
“Your facility’s RSSI measurement chart”
Confirm that the RSSI for all locations is 50 or less.
This step may require 1-2 hours to complete, depending on your
facility.
Pass
Fail
Test performed by ______________________________________________________ Date _____________
Facility
_____________________________________________________________________________________
Table 5. Final system check for wireless Acuity LT System (continued)
Step
Activity
Pass/fail
(circle
one)
Comments