beautypg.com

EFCO S5500 SSG Captured User Manual

Page 58

background image


EFCO CORPORATION 6/2012

PART NO. Y556

Page 58 of 81

S-5500 SSG and Captured Corner Mullion Installation Instructions

Section IX: Vertical Splice Joints

Installation for Captured System




ADJACENT UPPER

FRAME ASSEMBLY

UPPER FRAME

ASSEMBLY

LOWER FRAME

ASSEMBLY

STEP #3 ALIGN AND STACK ASSEMBLED FRAMES

A. Align the pre-assembled frames, and stack together at the splice joints.

B. Position the mullions to the appropriate elevation with regard to established

benchmarks, and shim or fix the mullions at their respective dead load anchor points.

C. Install both of the upper adjacent frames before sealing the mullion splice joints.
D. Clean the splice sealant-contact areas per sealant manufacturer’s recommendations.