S-5500 SSG and Captured Corner Mullion Installation Instructions

Section VII: Glazing Preparation

(Vertical SSG and Captured Horizontal)







STEP #1 SEAL JOINTS AT CORNER HEAD AND SILL AND AT CORNER MULLION

B. Seal between the mitered ends of the heads, sills, and the corner mullion to form a

wate-tight joint as shown in the detail below. The sealant must not obstruct or interfere

with the areas of the head or sill where the cover will engage. Note that this is a critical

primary seal.

C. Before applying the corner mullion glazing adapter, apply two beads of sealant to the

corner mullion as shown below at each intersection of the head, sill, and intermediate

horizontal. The corner mullion glazing adapter must be set immediately after this step
before the sealant begins to cure.

CAPTURED SILLS AT

SSG CORNER

Seal between the mitered ends

of the sills and the corner
mullion. Fill all voids

completely and tool smooth.

Apply two beads of sealant in the

reglets of the corner mullion where
the corner mullion glazing adapter

mates into the corner mullion.

Note: The corner mullion
glazing adapter must be set

immediately after applying

the sealant and before it

begins to cure.

CORNER

MULLIONS

CAPTURED

SILL

SSG CORNER

MULLION GLAZING

ADAPTER

Insert the end of the

adapter behind the
notches in the sills.

Attach the glazing adapter to

the corner mullion with the
required fasteners. Cap seal the

fastener heads with sealant.