S-5500 SSG and Captured Corner Mullion Installation Instructions

Section II: Frame Unit Assembly & Frame Sealing

SSG System


Under certain circumstances, it may be necessary to use drop-on heads and sills with mullion

‘M’ and ‘F’ anchors. Refer to alternate anchorage methods section for more information.

Apply sealant to the

face of the shear

blocks as shown.

FORMED ALUM.

SHEAR BLOCK

‘M’ ANCHOR

DROP-ON SSG

SILLS OR HEAD

SSG SILL CONDITION AT CORNER WITH ‘M’ ANCHOR

AND DROP-ON HORIZONTALS (HEAD SIMILAR)

Mitered end of

head or sill

Apply sealant to the ends of

the horizontals as shown.

Apply sealant between

the thermal struts as
shown, and tool smooth.

Note: Sealant must be applied to the ends of

each horizontal member before assembly.

SSG SYSTEM SHOWN -

CAPTURED SYSTEM

SIMILAR

After each frame unit

assembly is complete,
wipe off all excess

sealant and allow the

frame unit to cure.

Refer to “Section II: Frame

Unit Assembly &

Frame

Sealing” of the Series 5500

Outside Glazed or Inside

Glazed Installation

Instructions for additional

information.

Plug with backer

rod, and fill void
with sealant.

BUILDING