EFCO S5500 SSG Captured User Manual
Page 22
![background image](/manuals/635998/22/background.png)
EFCO CORPORATION 6/2012
PART NO. Y556
Page 22 of 81
S-5500 SSG and Captured Corner Mullion Installation Instructions
Section IV: Alternate Anchorage Method
STEP #1 INSTALL FRAME COMPONENTS
This method of anchorage is available for conditions where the standard head and sill anchors or
alternate head anchors are not adequate for the given design criteria. Please consult with the
structural engineer responsible for the shop drawings for your project.
A. Assemble verticals and intermediate horizontals following the frame assembly and sealing
instructions in Section II. Shear blocks should be installed after the frames are set and
anchored to avoid interference with the anchor bolts.
B. Insert ‘M’ anchors into each end of the intermediate verticals and corner mullion.
C. This section covers the installation for corner conditions. Refer to “Section V: Alternate
Anchorage Method” of the Series 5500 Outside Glazed or Inside Glazed Installation
Instructions for additional information.
‘M’ ANCHOR
‘M’ ANCHOR
CORNER MULLION
INTERMEDIATE
VERTICAL
PRE-ASSEMBLED
FRAME UNITS
CORNER ‘M’
ANCHOR
DEAD LOAD
SHIMS
CORNER ‘M’
ANCHOR
SSG SYSTEM SHOWN –
CAPTURED SYSTEM SIMILAR