Initial start-up, Notice – Wheatheart X160 Series User Manual
Page 119

W
HEATHEART
- G
RAIN
A
UGERS
6. O
PERATION
X160-85, X160-105, X160-125
30875 R0
119
6.3.1. I
NITIAL
S
TART
-U
P
Before Operating in the Normal Forward Mode:
1. The stub spline on the PTO driveline must be inserted into the Forward spline
coupler (see Figure 6.6) and securely locked into place.
2. Make certain the clean out cover is secured into place on the boot before
operating.
3. The PTO drive control on the tractor must be in the off position before starting
tractor and the PTO hazard area is clear of all bystanders.
Note:
All safety shields must be in place before operating.
B
REAK
I
N
Your auger does not require an elaborate break-in. However, following a few
simple tips during the initial operation can add to the reliability and life of your
machine.
If any unusual noises or vibrations are encountered, determine the source, shut
the auger off, lock out the power source, and adjust. If unsure of the problem or
procedure, contact your local Westfield dealer.
Important:
When starting the auger for the first time, be prepared for an emergency
shutdown in case of excessive vibration or noise.
1. Ensure that you have completed the checklist on page 115.
2. If everything is satisfactory, prepare for a 60 minute operation at half speed.
3. Ensure that the intake hopper is correctly positioned.
4. Ensure that the PTO drive on the tractor is in the OFF position.
5. Start the tractor and idle at low rpm. Slowly engage the PTO drive.
Note:
The auger may run rough until the tube is polished.
6. Gradually begin feeding grain into the hopper, bringing the tractor PTO speed
up to about 500 rpm. Do not overfeed the hopper on initial loads; keep the
feed of grain at about half capacity.
7. After the auger tube is polished and runs fairly smoothly, proceed to unload
at full PTO speed of 1000 rpm.
8. Upon completion of the initial run, slow the auger down. Stop the auger when
it is empty of grain.
9. Lock out the tractor and conduct a complete inspection of the auger following
Important:
After the initial start-up and inspection, the auger should be shut down and
inspected at least 3 more times during the first 10 hours of operation.
NOTICE
Do not run an empty auger at high speed; this results in