GENERAL MAINTENANCE

Verify daily that the operating parameters have

not varied significantly from the normal. A drastic

change in high voltage, operating current, turbine

air, or shaping air, can be an early indicator of

potential component failure.

A laminated poster entitled “Rotary Atomizer

Checklist” (AER0075-02) is included with the

assembly in the Literature Kit to be posted near

the station as a handy reference.

Due to the close proximity of high voltage to

ground potential, a schedule must be developed

for equipment maintenance (cleanliness).

PREVENTIVE MAINTENANCE

Daily Maintenance (During Each Preventive

Maintenance Break)

1. Verify that high voltage is OFF and that both

inner and outer shaping air, bearing air, and

turbine drive air are ON.

2. Open the dump valve, flushing all paint from

the supply lines and valve module.

3. Open the solvent valve, flushing all paint

from the fluid tube and through the atomizer

bell assembly.

4. Re-verify that high voltage is OFF, turbine

drive air is OFF, and that the bell cup has

stopped spinning. The bearing air and

shaping air should remain ON.

5. Clean all external surfaces of the applicator

using a lint-free rag dampened with solvent.

6. After cleaning, all conductive residue must

be removed using a non-conductive solvent.

Since electrostatic equipment is involved,

these solvents should also be non-polar

(Naphtha).

7. Inspect bell cup for nicks, dents, heavy

scratches, or excessive wear. Replace if

necessary.

8. Check bell cup tightness. Tighten to 50-70

lbs•in (5.65-7.91 Nm) torque.

9. Check the amount of paint build-up on the

outer protective cloth covers, if used. If

excessive, replace covers as required. If

cloths are wet, find source and replace with

dry cloth covers.

W A R N I N G

!

†

The high voltage must be turned OFF be-

fore entering the spray area and performing

any maintenance procedures. Spray booth

exhaust fan(s) should remain ON while

cleaning the equipment with solvents.

†

Make sure high voltage is OFF before

approaching applicator with solvent cloth.

†

DO NOT use reclaim solvent containing

d-Limonene. This can cause damage to

certain plastic components.

†

DO NOT stop bell rotation by using a rag

or gloved hand against the bell cup edge.

C A U T I O N

!

†

Maximum flow rate should not exceed

800 cc/min.

†

Daily removal and soaking of the bell cup

may not be required if the bell cup is properly

flushed. However, the frequency of the feed

tube and internal motor shaft inspection indi-

cated below under weekly maintenance can

be done daily and later adjusted to weekly or

as required depending on the results of the

inspection.