Install battery trays, Figure 33 battery trays, Table 2 conduit size - input feed – GE Industrial Solutions H5692448 Power Systems Infinity M1 (NE-M) User Manual
Page 26

NE-M
Installation Guide
H5692448
CC848815325 r06 May 2013
26
Table 2 Conduit Size - Input Feed
Rectifiers
per
Conduit
Rectifiers
per feed
Min.
External
Breaker
Wire
Gage
Minimum Conductor Rating
Conductors per
Conduit
Conduit
Size
AC Feeds – All rectifiers except NE075AC48xxxx
7
1
20A
10
40A*0.87*0.5 = 17.5A Rating
15 (50% derated)
1”
10
1
20A
10
40A*0.87*0.4 = 17.5A Rating
21 (40% derated)
1-1/2”
6
2
40A
8
55A*0.87*0.8 = 38.3A Rating
7 (80% derated)
1”
8
2
40A
6
75A*0.87*0.7 = 45.6A Rating
9 (70% derated)
1-1/2”
AC Feeds –NE075AC48xxxx Only
6
1
30A
6
75A*0.87*0.5 = 32.6A Rating
13 (50% derated)
1”
10
1
30A
4
95A*0.87*0.4 = A Rating
21 (40% derated)
1-1/2”
6
2
60A
A*0.87*0.8 = 3A Rating
7 (80% derated)
1”
8
2
60A
*0.87*0.7 = A Rating
9 (70% derated)
1-1/2”
PV Feeds
7
1
15A/300Vdc
10
40A*0.87*0.5 = 17.5A Rating
15 (50% derated)
1”
10
1
15A/300Vdc
10
40A*0.87*0.4 = 17.5A Rating
21 (40% derated)
1-1/2”
Install Battery Trays
Optional battery trays are suitable for use with general trade batteries such as Northstar Battery NSB110FT and
NSB170FT.
Step
Action
1
Position the battery tray in the frame with frame
mounting brackets on both front and back of frame as
shown.
Secure with provided screws.
Torque to 35 in-lb – 5/16” socket.
Figure 33 Battery Trays
13
Based on NEC 90°C Conductor, Number of Wires in Conduit, and 45°C Ambient
14
Including 1 ground per conduit
15
AC and PV feeds must be in separate conduits.