Battery or battery stand mounted frame, Connect central office ground (cog), Figure 18 ground short frame – GE Industrial Solutions H5692448 Power Systems Infinity M1 (NE-M) User Manual
Page 20: Figure 19 co ground landing

NE-M
Installation Guide
H5692448
CC848815325 r06 May 2013
20
Battery or Battery Stand Mounted Frame
If required by local code or practice, battery or battery stand mounted frames may be grounded to the frame or chassis
of the other equipment. Select a Frame Ground landing at the side of the frame and clean.
Step
Action
1
Secure Frame Ground connection with provided
hardware:
(2) ¼-20 x ¾” HH Bolt
(2) ¼-inch lock washer
(2) ¼-inch flat washer
If required by local code or practice, treat with an
oxidation inhibitor such as NO-OX.
Torque to 65 in-lb - 7/16” socket.
Note: Lug landings are 1/4” on 5/8” centers.
Figure 18 Ground Short Frame
Connect Central Office Ground (COG)
Step
Action
1
Secure COG connection with provided hardware:
(2) 3/8-16 nut
(2) 3/8-inch lock washer
(2) 3/8-inch flat washer
If required by local code or practice, treat with an
oxidation inhibitor such as NO-OX.
Torque to 240 in-lb - 9/16” socket.
Figure 19 CO Ground Landing
Note: Lug landings are 3/8” on 1” centers.