NE-M

Installation Guide

H5692448

CC848815325 r06 May 2013

19

Step

Action

1

Verify that the rack is positioned to provide adequate ventilation space to the rear of the equipment: 4” to

solid surface, 6” to heat producing surface.

Distance required to rear of mounting rails: 16.5” to solid surface, 18.5” to heat producing surface.
Position the sub-frame system in the rack as desired.
Secure the sub-frame system into the rack with at least (12) frame mounting screws, 6 screws per side.

Torque to 35 in-lb – 5/16 socket.

Figure 16 Mount Sub-Frame

Ground Frame

Floor Mounted Frame

Select a Frame Ground landing on the top of the frame and clean.

Step

Action

1

Secure Frame Ground connection with provided

hardware:

(2) ¼-20 x ¾” HH Bolt
(2) ¼-inch lock washer
(2) ¼-inch flat washer

If required by local code or practice, treat with an

oxidation inhibitor such as NO-OX.

Torque to 65 in-lb - 7/16” socket.

Note: Lug landings are 1/4” on 5/8”and 1” centers.

Figure 17 Ground Frame

Use either of two frame

ground lug landing

locations.