Before you install a main unit or expansion unit, perform the following tasks:
•
Determine the location for the BCM50 units, telephones, and other equipment based on space
and electrical requirements.
•
Order the required trunks from the central office.
•
Ensure that you have all the equipment and supplies you need to install the system.
For information about BCM50 installation prerequisites:
•
•
•
Site telephony wiring requirements
•
System equipment, supplies, and tools
Environmental requirements
Ensure you meet the installation environmental requirements. The installation area must be:
•
a minimum of 4 m (13 ft.) from equipment such as photocopiers, electrical motors, and other
equipment that produces electromagnetic, radio frequency, and electrostatic interference
•
within 1.5 m (5 ft.) of a three-wire grounded electrical outlet
•
clean, dry, well ventilated, and free of traffic and excess dust
•
within the temperature range of 5°C and 50°C (40°F and 120°F)
•
from 20% to 80% non condensing relative humidity
•
structurally strong and with enough space to support the BCM50 units
•
a minimum of 46 cm (18 in.) from the floor
Electrical requirements
Ensure you meet the following electrical requirements:
•
Power must be supplied from a non switched, unobstructed outlet within 1.5 m (5 ft.) of the
BCM50 units.
•
The supplied power must be a dedicated 110 V to 120 V AC nominal (or 220 V to 240 V AC
nominal), 50 to 60 Hz, 15 A minimum service with a third-wire safety ground. The third-wire
safety ground provides shock protection and prevents electromagnetic interference.
Note: The installation area must be of sufficient height from the floor to prevent water