Welcome to Advanced PC Configuration

23

Commissioning PC Stations - Manual and Quick Start
Release 5/2005

C79000-G8976-C156-07

S

Case b) Initial configuration with existing project engineering (XDB file)

With this method, it is assumed that the PC station and its components and
applications is first created in project engineering in STEP 7 / NCM PC. This
produces a database (XDB file) that is then available for the commissioning
engineer for the initial configuration.

The advantage of this is that the project engineering data and the PC
configuration are consistent and the total effort is minimal.

Step

How does it work?

Tool

Project engineering

(as prerequirement for
initial configuration)

Steps in project engineering of the PC
station:

S

Create the PC station in NCM PC

NCM PC / STEP 7

S

SIMATIC Manager

S

Enter modules and applications

S

HW Config

S

Create connections in NetPro

S

Use symbols (in the project
engineering of the OPC server)

S

NetPro

S

HW Config

S

Project engineering data of the PC
station is saved in an XDB file .

S

SIMATIC Manager

1. Installing SIMATIC

NET software

Install the SIMATIC NET software
based on the installation instructions

SIMATIC NET CD / Windows

2. Installing the

hardware (PC
modules)

Install the communication module in the
PC station

Refer to the documentation on the
CP

3. Initial configuration

Import XDB

Project engineering data is transferred
to the PC station.

Station Configuration Editor

(later download of project
engineering data also possible
with NCM PC / STEP 7)

Result:

PC station is ready for productive communication

4. Testing the

configuration

Configuration Console

Configuration Console