13.8
Project Engineering for a PC Station as DP Slave
This section explains how to create the project engineering for a PC station with
the CP 5611 as DP slave.
Two situations can be distinguished:
S
The DP master engineering data was created in NCM/STEP 7 (in the example
as other PC station)
S
The engineering data for the DP master cannot be created in NCM / STEP 7
In both cases, a CP 5611 is used as the DP slave. We assume a project in which a
DP master system has been created (for a description of creating the system, refer
to Section 13.5).
13.8.1
DP Master is Known in NCM / STEP 7
As an example, we first create a PC station that can take on the role of a DP slave.
Follow the steps below:
Follow the steps outlined below:
1.
Open the project with the DP master system.
2.
Insert a PC station from the catalog.
The PC station adopts the role of the DP slave.
3.
Open the PC station in HW Config.
4.
Add a user application of the type OPC server or application in the PC station.
5.
Insert a module of the type CP 5611.